-29.00 |
2024 Pavement Preservation Program Microsurface, Chip Seal, and Asphalt Patching Various Locations in City |
Vance Brothers, Inc. |
$518,921.12 |
04/15/2024 |
-28.00 |
Augusta Municipal Airport Project No. 3-20-0006-021, Runway 18/36 Reconstruction and Extension, Base Bid & Alternate Bid No. 1 |
Dondlinger Construction |
$6,809,032.70 |
6/19/2023 |
-27.00 |
2023 Pavement Preservation Program |
Vance Brothers, Inc. |
$498,172.92 |
4/3/2023 |
-26.00 |
CCLIP - KDOT Project No. 008 U-2422-01 US 54 East End BNSF Overpass to East City Limits 7th St |
APAC |
$442,286.88 |
2/6/2023 |
-25.00 |
2023 Custom Cab Fire Pumper Truck |
Weis Fire |
$533,503 |
6/20/2022 |
-24.00 |
Rehabilitation of Lakeside and Simmons Lift Stations |
McCullough Excavation |
$692,000 |
2/22/2022 |
-23.00 |
North Ohio Street Reconstruction and Belmont Avenue Pedestrian Trail |
Kansas Paving |
$1,872,776.46 |
2/22/2022 |
-22.00 |
2022 Ford Explorer Police Vehicle |
Rusty Eck Ford |
$35,997.00 |
2/7/2022 |
-21.00 |
Taxable General Obligation Refunding Bonds |
Robert W. Baird & Co., Inc. |
$2,154,598.83 |
2/7/2022 |
-20.00 |
Wastewater Division 3/4-Ton Pick-Up |
Shawnee Mission Ford |
$45,898 |
1/17/2022 |
-19.00 |
Electric Distribution Division 3/4-Ton Pick-Up |
Shawnee Mission Ford |
$45,898 + Sales Tax |
1/17/2022 |
-18.00 |
Street Division 1-Ton Pick-Up |
Shawnee Mission Ford |
$47,309 |
1/17/2022 |
-17.00 |
Solid Waste Division 3/4-Ton Pick-Up |
Shawnee Mission Ford |
$45,898 |
1/17/2022 |
-16.00 |
Solid Waste Division 1/2-Ton Pick-Up |
Winfield Motor Company |
$36,133 |
1/17/2022 |
-15.00 |
Demolition of Single Family Residential Structure and Detached Residential Garage at 234 E Broadway Ave |
State's Dirtwork, LLC |
$9,951 |
1/17/2022 |
-14.00 |
Demolition of Structure at 926 North Lulu Street |
Alan's Excavating |
$11,900 |
9/20/2021 |
-13.00 |
State Street Water Tower Re-Painting |
Viking Painting, LLC |
$265,400 |
9/20/2021 |
-12.00 |
Automated Tarping System |
Fleet Pride |
$10,825.51 |
6/7/2021 |
-11.00 |
Lulu to Frisco Pedestrian Trail Project Construction |
APAC - Kansas |
295,062.55 |
3/15/2021 |
-10.00 |
2021 Insurance Policy Renewal |
ICI Insurance |
$452,402 |
3/15/2021 |
-9.00 |
Two 2021 Ford Explorer Police Vehicles |
Rusty Eck Ford |
$55,258 |
2/16/2021 |
-8.00 |
Water Division 1-Ton 4x4 Pick-Up |
Winfield Motor Company |
$30,523 |
2/1/2021 |
-7.00 |
Double-Wall Fuel Tanks and Fuel Master System |
Double Check Co. Inc. |
$29,930.64 |
12/21/2020 |
-6.00 |
WWTP Furnace System Replacement |
Central Consolidated Inc. |
$24,983 |
11/2/2020 |
-5.00 |
Slurry Seal Maintenance on Money and Lulu Street |
South Central Sealing & Paving |
$63,327.16 |
8/17/2020 |
-4.00 |
Asphalt Pavement Preservation |
Proseal, Inc. |
$73,277.54 |
7/6/2020 |
-4.00 |
Conducting a Housing Study |
Canyon Research Southwest Inc. |
$5,000 |
8/3/2020 |
-3.00 |
Issuance, Sale, and Delivery of General Obligation Temp Notes |
Country Club Bank |
0.84% Interest Rate |
6/15/2020 |
-2.00 |
Public Safety Telephone System Upgrade |
Communications Technology Associates, Inc. |
$9,699.82 |
3/16/2020 |
-1.00 |
Renewal of City Insurance Policy |
Madrigal & Welch |
$428,613.00 |
3/16/2020 |
0.00 |
2020 Ford Explorer Police Vehicle |
Rusty Eck Ford |
$37,487.00 |
2/18/2020 |
1.00 |
Street Division Mid-Sized Dump Truck |
Shawnee Mission |
$94,154.00 |
1/20/2020 |
2.00 |
HVAC System Replacement at WWTP Operations Building |
Fahnestock |
$11,327.00 |
1/6/2020 |
3.00 |
Parks & Recreation Division Work Truck |
Winfield Motor Company |
$25,109.00 |
11/18/2019 |
4.00 |
Community Hangar Drive Reconstruction Project |
Vogts-Parga Construction, LLC |
$33,544.00 |
11/4/2019 |
5.00 |
Public Safety and City Hall Server Upgrades |
TK Fast |
$94,204.00 |
8/19/2019 |
6.00 |
Airport Liability Insurance |
Old Republic |
$1,381.00 |
4/1/2019 |
7.00 |
Wastewater Treatment Plant SCADA System Panels |
Norberg IES, LLC |
$109,460.00 |
4/1/2019 |
8.00 |
2019 City Insurance Policy |
Madrigal & Welch |
$410,844.00 |
3/18/2019 |
9.00 |
Police Patrol Vehicles (2) |
Rusty Eck Ford |
$46,394 |
2/19/2019 |
10.00 |
Electric Plant Sanitary Sewer Line Installation |
Dondlinger Construction |
$30,508 |
2/19/2019 |
11.00 |
Mini Excavator - Water Department |
White Star Machinery & Supply |
$28,300.00 |
1/21/2019 |
12.00 |
Toro Groundmaster Rangewing Mower |
Professional Turf Products, L.P. (Sourcewell national contract) |
$67,286.15 |
1/21/2019 |
13.00 |
WWTP Control Panels, Wiring, Installation |
Mid-State Pipeline Maint. |
$396,100.00 |
12/3/2018 |
14.00 |
WWTP SCADA Instruments |
Various Vendors |
$85,269.06 |
11/19/2018 |
15.00 |
Appcon 2nd Addition Water & Sewer Improvements |
Mies Construction |
$39,198.50 |
11/5/2018 |
16.00 |
Animal Control Side-In Unit |
Jones Trailer Company |
$4,897.91 |
11/5/2018 |
17.00 |
Animal Control Vehicle |
Davis Moore Automotive |
$20,215.00 |
10/15/2018 |
18.00 |
WWTP Commercial ZTR Mower |
Wichita Tractor Company |
$7,702.00 |
10/15/2018 |
19.00 |
Public Safety Patrol Vehicles (2) |
Rusty Eck Ford |
$44,874.00 |
5/21/2018 |
20.00 |
Dog Park Fence |
Quality First Fence |
$25,401.61 |
4/2/2018 |
21.00 |
2017 Street Sales Tax/ Lake Road Improvements |
APAC-KS Inc. |
$852,921.60 |
4/16/2018 |
22.00 |
City Website Update |
Revize |
$19,700.00 |
2/5/2018 |
23.00 |
Santa Fe Lake Utility Vehicle |
Mid-America Powersports |
$7,609.95 |
12/18/2017 |
24.00 |
Sanitary Sewer Basin A Improvements |
SAK |
$1,561,637.80 |
12/4/2017 |
25.00 |
Garvin Park Restroom/Concessions Facilities |
Sauerwein Construction |
$651,500.00 |
10/2/2017 |
26.00 |
Demolition 347 Main Street |
Alan's Excavating Inc |
$3,500.00 |
8/7/2017 |
27.00 |
Demolition 331 and 347 E. 5th Avenue |
Alan's Excavating Inc. |
$6,650.00 |
6/19/2017 |
28.00 |
Demolition 1117 N. School Street |
ABC Demolition Services |
$2,000.00 |
8/7/2017 |
29.00 |
Meadowview Acres Earthwork |
Alan's Excavating Inc. |
$9,975.00 |
5/1/2017 |
30.00 |
Ohio Street Project Field Testing Services |
Terracon |
$14,905.00 |
5/1/2017 |
31.00 |
Wastewater Division Service Truck |
Winfield Motor Company |
$29,901.00 |
3/6/2017 |
32.00 |
Splash Pad Fence Bids |
Wichita Fence Company |
$10,598.90 |
3/6/2017 |
33.00 |
South Ohio Street Project - KDOT |
Kansas Paving |
$3,119,888.05 |
2/21/2017 |
34.00 |
Public Safety Patrol Vehicle |
Don Hattan Chevrolet |
$26,964.00 |
2/21/2017 |
35.00 |
Audit Services for Years 2021-2023 |
Gordon CPA LLC |
$48,525 |
11/1/2021 |
36.00 |
Augusta City Lake Dam Repairs |
Alan's Excavating |
$334,520 |
10/2/2023 |